Cafeteria Expansion Updates

6/18/18 - 6/22/18
Job site set up with barricades, there will be chain link fencing to keep out of job site.
 
The entire lower parking lot will be off limits for the duration of the project (staging area for construction crew and access of large equipment and vehicles). This is a safety measure so that we have no one entering into the construction zone.
 
Demolition on the inside of the dining room and all rooms inside that area will be done first, then the major demolition work will take immediately after.  The plan is to finish all of the major demolition prior to the start of school, then construction work to begin. 
 
 
Update on cafe expansion project (as of 7/6/18)
 
A chain link fence to mark the construction zone has been put up. No entry to the construction site at any time. Reminder: the lower parking lot and access to our campus/field from Lumiaina Street will be completely closed off for the duration of the project.

Major demolition work is set to begin next week (July 9 - 13) during normal work hours. Expect noise and dust to be at its highest during this time. The construction company is trying to complete the demolition work before school starts.